  • Continue with removals for Phase 1A and storm sewer construction.
  • Grading and utility relocation work along northeast noise wall
  • Temperature dependent, seeding behind south noise wall
  • Construct retaining wall by Omaha Storage

April 2, 2018

  • Continue construction of box culvert extension and junction box
  • Grading and utility work to begin along northeast noise wall
  • Surface removal along south side of Phase 1A work area