CONSTRUCTION UPDATE:

July 8, 2019: Finish prep work on 152nd St. north and pave street, followed by driveway construction; Continue grading Harrison St. median and pouring inlets; Work on south side sidewalk and driveways; Continue noise wall staining, move to wall #1; Continue retaining wall construction with phase 2; temporary median cross over at 151st St. in place until 150th St. construction is complete.

-Planning to open phase 2 to traffic the week of July 16th, and close phase 3 for construction.

-Seeding behind noise wall #1 is on hold until later this fall.

THIS MILE-LONG ROADWAY PROJECT IS BEING IMPROVED FROM A TWO-LANE TO A FOUR-LANE ARTERIAL WITH TURN LANES AND MEDIANS.

The improvements will reduce travel time and congestion as well as improve safety. Construction is being completed in phases to minimize impacts for local access.

Click here for detailed construction phasing for 2019.

QUESTIONS?

Get in touch with our project team

 

 

Harrison Street Project Aerial Harrison Street Project Aerial       * click above image to open a larger version           

The latest from our Twitter account:

The latest from our Facebook page:

Harrison Street Project
Harrison Street Project7 days ago
Significant progress made the last two weeks thanks to dry weather! ☀️